Major Facility Improvements Since 2012

Begun in 2013, our membership program has provided revenue that has been reinvested directly into equipment and facilities for the benefit of our members. Below is an outline of the tangible strategic  improvements made possible by this fee reinvestment.  Less visible, and critically important are the maintenance and repair of our equipment and facilities also supported by our fee structure.   The long term strategic plan is continually informed by our survey data

 

2013: 

Urgent replaster of alumni pool and major repair of mechanical system

Braun Athletic Center updates, flooring, paint, locker room improvements, new men’s lockers

Began cardio equipment additions and strength equipment replacement process

 

2014:

Continue equipment replacement and rotation program,

Add selectorized weight circuit machines

Create new barn outdoor weight room

 

2015:

Resurface tennis courts and add shade structures, 

Add more cardio exercise machines,

Create vertical climbing wall in Brown Gym.

 

2016: 

Convert north field to synthetic turf for baseball and soccer. 

Equipment preventive maintenance service initiated.

South Field and Pool service vendors initiated.

 

2017: 

Create Brown south weight room as a third weight room.

Add additional bleachers to the Braun Gym. 

Create small women’s locker room in Brown Gym. 

Replace all Tennis fencing

 

2018: 

Replace track with Mondo surface, install shade structure and windscreens at track.

 

2019: 

Update and move bouldering cave to outside, 

Create kayak and surf club shed on south side Brown. 

Create family change room off of the pool deck.

 

2021: 

Replace all outdoor lighting with efficient, playing surface lights, south field, tennis courts, pool.

 

2022: 

Resurface tennis courts and add 4 pickleball lines

Create AG shower space in Braun.

create tennis parkway with seating area and better landscaping

 

2023: 

Major renovation of Brown locker room: 

     new lockers and all new plumbing, 

     new access and lobby, 

Brown gymnasium, resurface floor, new hoops, paint, add curtain,

Create brown south patio as usable space, 

Update athletic training medical space, update laundry service.

 

Future Projects:

Create a new cardio corridor, stretch lab and spinning room in Brown (more useable exercise spaces)

Light the North Field (Allow for double the useable nighttime outdoor play space)

Convert pools to a 50m pool (Better meet expectations for open swim space throughout the year)

Air condition the Brown locker rooms and Gym

Scott H. Brown Gym Renovations
 

In response to member input and with the aim of further enhancing our recreational facilities and services to meet member needs, Scott H. Brown Gym is undergoing a yearlong multi-phase renovation project. 

Upgrades begin in April 2023 with a renovation of the main locker room. A complete outline of the work for each phase of the project can be found below, with information on expected project timelines and changes to member access or use of a targeted space. As each phase is complete, we will reopen the recently completed work area to members for use.

The renovations are being supported by our more than 4,000 members, as we are able to reinvest membership fees to fund each of these enhancements. 

Thank you for your support and understanding as we move forward with this work. We remain committed to providing all of our members with access to recreational facilities and services throughout the project and we will work to limit disruption to your exercise time or use of the facility. Updates on the project will be posted as progress is made and we will notify the community of any changes or unplanned interruptions as they may be required. 

Artist's rendering of renovated locker room

Before: 

After:

Brown Gym - New

Phase 1: April 2023-September 2023 

Planned Improvements:

  • Convert Brown Men’s locker room into two co-equal 1,250 sq ft men’s and women’s locker rooms with 400 new lockers and private changing stalls, new plumbing, lighting, flooring, and paint.
  • Create two new lockable, individual, non-gendered private showers, toilets, and changing spaces.
  • Restore the central access point for all athletic facilities to the Brown Gym. This will streamline entry/exit to the facilities as it allows for better flow of facility users to locker rooms and then to exercise/play spaces.
  • Repair air circulation system.

Temporary Impact to Members During Renovations:

All members who need access to change workout clothes or take a shower will use the facilities in Braun Athletic Center, main floor.  There is a small number of lockers available for overnight use (see the front desk).  Most members should be prepared to carry their gear to and from the gym this summer.  The Brown Gym will remain open for play this summer.  There may be temporary access issues due to safety or construction and we will prioritize clear and timely communication about those instances.

See conceptual photos and floor plan below.

Phase 2: Fall of 2023

Planned Improvements:

  • Install locker room heating and cooling units.
  • Brown Gymnasium Enhancements: Add curtain divider, re-line and re-surface the gym floor, remove broken bleachers, add wall pads, and paint facility. Upgrade and improve equipment storage.

Temporary Impact to Members During Renovations:

Unknown at this time, but as the plan comes into focus, impact will be assessed and scheduled at the lowest impact as possible and communicated in advance.

Phase 3: Summer 2024

Planned Improvements:

  • Install heating and cooling unit for Brown Gym.
  • Relocate Cardio corridor to north side of Brown with view of the mountains.

Temporary Impact to Members During Renovations:

Unknown at this time, but as the plan comes into focus, impact will be assessed and scheduled at the lowest impact as possible and communicated in advance.  Maintaining use of the cardio equipment and open play spaces are our priorities and we will plan accordingly.

Future, Long-term Improvement Projects: 

The timeline and funding to support the following enhancements is still being finalized.

2025: Install lighting to the North Field to increase accessibility for all members during winter months and later evening hours.

2026: Complete renovation of the pools to one 50-meter tank, complete mechanical system overhaul.